Area roadwork this week:
I-95 Northbound
Exit 143 (Aquia/Garrisonville)
Sunday – Monday, 10 p.m.-4:30 a.m., and Monday – Thursday, 9 p.m.-4:30 a.m. Milling and paving near exit 143 (Aquia/Garrisonville) between mile markers 142-145 in Stafford County. Single lane closures begin at 10 p.m. Sunday night and 9 p.m. Monday-Thursday nights, and double lane closures begin at 11 p.m. Sunday and at 10 p.m. all other nights. All northbound lanes reopen by 4:30 a.m.
Exit 143 (Aquia/Garrisonville) Ramp Closures
Sunday – Monday, 10 p.m. – 4:30 a.m. I-95 northbound off-ramp to Route 1 will close for milling and paving operations.
Monday – Tuesday, 10 p.m. – 4:30 a.m. I-95 northbound on-ramp from Route 610 and I-95 northbound off-ramp to Route 610 westbound toward Garrisonville will close for milling and paving operations.
Wednesday – Thursday, 10 p.m. – 4:30 a.m. I-95 northbound off-ramp to Route 1 will close for milling and paving operations.
City of Fredericksburg
Monday – Friday, 7 a.m. to 5 p.m. Brief, intermittent road closures impacting traffic on Sam Perry Boulevard and Hospital Drive (Mary Washington Hospital) for Dominion Energy utility work. If you are experiencing an emergency and are encountering traffic delays, please call 911.
Caroline County
Route 1
Monday – Friday, 9 a.m.-3 p.m. Single lane closures and shoulder closures between Ladysmith Road and Route 207 (Rogers Clark Boulevard). Fiber installation under permit.
Thursday – Friday, 9 p.m.-4 a.m. Full stoppages for fiber work under permit between Ladysmith Road and Durrette Road.
Route 17 (Tidewater Trail) Northbound
Monday – Friday, 7 a.m.-5 p.m. Pavement marking. Alternating lane closures between Hazelwood Lane and Mount Creek Bridge.
Route 207 (Rogers Clark Boulevard)
Monday – Friday, 7 p.m.-6 a.m. Paving. Alternating lane closures on northbound Route 207 between Polecat Creek bridge and Devils Three Jump Road, and on Route 207 southbound between the Mattaponi River bridge and the railroad bridge.
Route 639 (Ladysmith Road)
Monday – Friday, 9 a.m.-3 p.m. Alternating lane closures for fiber installation between Route 1 and Partlow Road.
Thursday – Friday, 9 p.m.-4 a.m. Full stoppages for fiber work under permit between Route 1 and Center Drive.
Route 676 (Devils Three Jump Road)
Monday – Friday, 7 a.m.-5 p.m. Pavement marking. Alternating lane closures between Route 207 and Nelson Hill Road.
King George County
Route 3
Sunday – Friday, 7 p.m.-7 a.m. Mobile pavement marking crew between Stafford County line and Westmoreland County line.
Monday – Friday, 9 a.m.-3:30 p.m. Guardrail work. Single lane closure on Route 3 eastbound near Route 694 (Lambs Creek Church Road).
Route 218
Monday – Friday, 9 a.m.-3:30 p.m. Guardrail work. Single lane closure on Route 218 near Machodoc Creek. Flagging crew will direct one-way, alternating traffic.
Route 716 (Foxes Way)
Sunday – Thursday, 8 p.m.-6 a.m. Alternating lane closures for milling and paving between Route 3 and cul-de-sac.
Spotsylvania County
Route 1 Southbound
Monday – Friday, 9 a.m.-3 p.m. Single lane closure on Route 1 southbound between Ladysmith Road and Massaponax Church Road for fiber installation under permit.
Route 1 Northbound
Monday – Friday, 9 a.m.-3 p.m. Single lane closure on northbound Route 1 between Ondura Drive and Guinea Station Road for waterline work under permit.
Route 1 Northbound
Sunday – Thursday, 8 p.m.-5 a.m. Right lane closure between Crossing Court and Market Street for construction of I-95 exit 126 area improvements.
Route 1 Southbound
Sunday – Thursday, 8 p.m.-5 a.m. Right lane closure between Market Street and the I-95 southbound off-ramp at exit 126 (Spotsylvania) for construction on I-95 interchange area improvements.
Route 1 at Route 606 (Mudd Tavern Road)
Monday – Friday, 9 a.m.- 3 p.m. Utility work at intersection. Flaggers will direct drivers through the work zone.
Route 3
Sunday – Thursday, 7 p.m.-6 a.m. Mobile lane closures for pavement marking work between Gateway Boulevard and Chewling Lane and between Bragg Road and Gateway Boulevard.
Route 17 (Mills Drive)
Monday – Friday, 9 a.m. – 3 p.m. Guardrail work. Alternating lane closures on southbound Route 17 near Route 2 and at the intersection of Route 608.
Route 208 (Courthouse Road/Lake Anna Parkway)
Sunday – Thursday, 8 p.m. – 6 a.m. Milling and paving at multiple locations with alternating lane closures for mobile operation.
Route 608 (Robert E. Lee Drive)
Monday – Friday, 9 a.m.-7 p.m. Paving, following recent shoulder widening work. Flagging crew will alternate one-way traffic between Route 208 and Catharpin Road.
Route 610 (Old Plank Road)
Tuesday – Friday, 9 a.m.-3 p.m. One-way, alternating traffic between Ziyad Drive and Gordon Road. Road widening project.
Route 620 (Harrison Road)
Monday – Wednesday, 9 p.m.-5 a.m. and Tuesday – Friday, 9 a.m.-3 p.m. One-way, alternating traffic between Gordon Road and Old Plank Road. Road widening project.
Route 627 (Gordon Road)
Monday – Wednesday, 9 p.m.-5 a.m. and Tuesday – Saturday, 9 a.m.-3 p.m. One-way, alternating traffic between Legacy Woods and Old Plank Road. Road widening project.
Route 634 (Flippo Drive)
Monday – Friday, 9 a.m.-5 p.m. Cape seal and pavement markings. Flagging crew will alternate one-way traffic between Guinea Road and Massaponax Church Road.
Stafford County
Route 1
Monday – Friday, 7 p.m.-7 a.m. Mobile alternating lane closures for pavement marking work between the City of Fredericksburg line and Prince William County line.
Wednesday – Thursday, Midnight-4 a.m. Full stoppage for installation of overhead utility lines under permit between Enon Road and Centerport Parkway.
Route 1 Northbound
Sunday – Thursday, 9 p.m.-5 a.m. Guardrail work. Single lane closure near Bells Hill Road/Coal Landing Road.
Route 1 Southbound
Monday – Friday, 9 a.m.-3 p.m. Single lane closure for guardrail installation at the intersection of Route 17.
Route 3
Monday – Friday, 7 p.m.-7 a.m. Mobile alternating lane closures for pavement marking work between City of Fredericksburg line and Route 3 and City of Fredericksburg line and King George County line.
Route 3 (Blue and Gray Parkway)
Sunday – Thursday, 8 p.m.-6 a.m. Alternating lane closures for milling and paving between Rappahannock River bridge and Route 3 Business (Kings Highway) and Route 680 (Leonard Road).
Route 3 (Kings Highway)
Sunday – Thursday, 8 p.m.-6 a.m. Alternating lane closures for milling and paving between Route 3 (Blue and Gray Parkway) and Route 713 (Federal Drive) and end of Chatham Bridge and Route 3 (Blue and Gray Parkway).
Sunday – Thursday, 9 p.m.-5 a.m. Single lane closure for guardrail installation near Naomi Road.
Route 17
Monday – Friday, 9 a.m.-3 p.m. Median improvements under permit. Expect alternating northbound and southbound lane closures on Route 17 between Poplar Road and the entrance to the Cardinal Forest subdivision.
Route 17
Sunday – Thursday, 7 p.m.- 6 a.m. Mobile operation for pavement markings between Route 1 and Short Street.
Monday – Friday, 7 p.m.-7 a.m. Mobile alternating one-way lane closures for pavement marking work between Fauquier County line and Sanford Drive.
Route 17 Southbound
Monday – Friday, 9 a.m.-3 p.m. Guardrail work. Single lane closure near Tensley Lane.
Route 218
Monday – Friday, 7 p.m.-7 a.m. Mobile alternating one-way lane closures for pavement marking work between Route 1 and King George County line.
Route 607 Northbound (Deacon Road)
Monday – Friday, 9 a.m.-3 p.m. Single lane closure for guardrail installation at the intersection of Route 218.
Route 607 (Cool Springs Road)
Monday-Tuesday, 8 p.m.-5 a.m. Turn lane closures for waterline work under permit.
Route 610 at Aquia Creek Bridge
Monday – Friday, 9 a.m.-3 p.m. Guardrail work. Flagging crew will alternate one-way traffic at the Aquia Creek bridge.
Route 626 (Potomac Run)
Friday, 9 a.m.-6 p.m. One-way alternating lane closures between Route 625 (Leeland Road) and Route 628 (Eskimo Hill Road) for paving repair work.
Route 627 (Mountain View Road)
Monday – Thursday, 7 p.m.-6 a.m. One-way alternating lane closures for pavement resurfacing between Kellogg Mill Road and Wood Road and between Carter Lane and Poplar Road. Flaggers will direct traffic through the work zone.
Route 630 (Courthouse Road)
Wednesday – Thursday, 7 p.m.- 6 a.m. Mobile operation for milling between Shelton Shop Road and Winding Creek Road.
Route 652 (Truslow Road)
Monday – Tuesday, 9 a.m.-3 p.m. Paving between Berea Church Road and Poplar Road. Flaggers will alternate one-way traffic through the work zone.
Brentwood Estates subdivision
Monday – Friday, 9 a.m.-7 p.m. Road resurfacing. Flagging crew will direct traffic on various routes for road resurfacing.
Spotsylvania County
I-95 Exit 126 Area Improvements
Route 1 is being widened to six lanes near the I-95 exit 126 interchange. This will provide space to build a second left turn lane for Route 1 traffic entering I-95 northbound and southbound. An auxiliary lane will be built on I-95 northbound from the on-ramp to the Route 208 (Courthouse Road) overpass to help entering vehicles merge with interstate traffic. The I-95 northbound and southbound on-ramps will be widened to receive traffic from dual left turn lanes. Two noise barriers will be built along I-95 southbound. Project completion is expected in Sept. 2027.
Route 620 (Harrison Road) Reconstruction and Widening
Harrison Road is being widened to four lanes between Gordon Road and Old Plank Road. The project will build a center turn lane along Harrison Road and additional through travel lanes at the Old Plank Road and Gordon Road intersections, and extend the current turn lanes at these intersections. Sidewalks will be built along Harrison Road, and pedestrian crossing signal equipment and crosswalks will be added at the Old Plank Road and Gordon Road intersections. Project completion expected in Sept. 2026.
Stafford County
Route 1 Bridge Replacement at Chopawamsic Creek
Construction is underway on a $13.9 million project to replace the four-lane Route 1 bridge over Chopawamsic Creek. The bridge is located just south of the Prince William County line and is near Quantico Marine Corps Base. Construction is expected to be complete in June 2028. Four travel lanes will remain open at most times during construction, with periodic lane closures needed during off-peak times as traffic is shifted to complete the bridge construction in phases.
Route 1 at Telegraph Road and Woodstock Lane
Construction is underway to realign the intersection of Route 1 and Telegraph Road, and to widen Route 1 at Woodstock Lane to build a southbound left turn lane and to make access management improvements. New traffic signal equipment will be installed at Telegraph Road and dual left turn lanes will be built from Telegraph Road onto Route 1 southbound. A left turn lane is being built from Route 1 southbound into Woodstock Lane. At Woodstock Lane, a concrete median will be installed on Route 1 to restrict turning movements. Stafford County is locally administering this project. Project completion in fall 2026. Visit the county project page.
Route 1 and Courthouse Road Intersection Improvement Project
Construction is underway to widen Route 1 and provide improvements at the intersection of Route 1 and Courthouse Road, and at the intersection of Route 1 and Bells Hill Road/Hope Road. Route 1 will be improved to have four lanes with a concrete median separating northbound and southbound traffic, with dedicated left turn lanes onto Courthouse Road, Bells Hill Road and Hope Road. Improvements will also be made on eastbound and westbound Courthouse Road approaching Route 1. An 8-foot-wide sidewalk will be installed along Route 1, with crosswalks. Stafford County is locally administering this project. Project completion expected in summer 2027. Visit the county project page.
Route 644 (Rock Hill Church Road) Bridge Replacement
Route 644 (Rock Hill Church Road) is closed to replace the temporary single-lane structure over Aquia Creek with a two-lane bridge. Rock Hill Church Road will remain closed to through traffic between Dunbar Drive and Van Horn Lane with a detour in place until June 2027.
Cmmuting and Ridesharing Information
GWRideConnect is a free ridesharing information and matching service for the Fredericksburg area and is part of the George Washington Regional Commission.
Let GWRideConnect help you discover your commuting options, such as carpools, vanpools, and transit. Visit www.gwrideconnect.org or call (540) 373-7665.